Timeline for Construction

Timeline for custom inground pool construction

30. June 2008

Step 1: Consultation and Design (1-4 weeks). Meet with designer/architect to plan the project in compliance with all limitations concerning size and location of the pool. Master Plans are drawn.

Step 2: Contract and Pricing (2 weeks +/-). The job is priced and a contract is written. The contract and pricing are reviewed by the homeowner and a payment schedule is discussed.

Step 3: Apply for County Permits (4-8 weeks). Review by County (3 days - 9 months). Obtain any necessary drawings (ie. structural drawings, grading plans, working drawings) for County permits.

Step 4: Apply for City Permits (2-5 days)

Step 5: Site Inspection and Preparation (1-2 weeks). Construction begins after permits are obtained.

Step 6: Construction (1 month +). The construction time will vary greatly by the scope of the job. Cost of construction is roughly $100,000 per month.